AIP Supplement

KAZAERONAVIGATSIA

AIP SUP

001/2026

Effective from 17 APR 2026 to 31 MAR 2028

Published on 17 APR 2026

  ALMATY AD (UAAA) - AERODROME CONSTRUCTION PLAN 2026-2028

 — INTRODUCTION

The purpose of this AIP Supplement is to inform operators of temporary closures of runways, taxiways, and aprons at UAAA - ALMATY / International Airport to facilitate aerodrome construction works during the 2026–2028 period. This document provides a detailed, phase-by-phase description of civil works, operational impacts, runway/taxiway closures, aircraft stand availability, and aircraft taxi routings for the duration of the construction period. The works are planned in several phases, as indicated below. These work and closure phases are subject to change in order to meet evolving operational and construction requirements.

 — Note:

The effective dates of specific area closures and more detailed information regarding affected activities will be provided via NOTAM and Safety Bulletins (to airport users) in advance of the closures.

 — PHASE 1 – Period March 1, 2026 – May 15, 2026

 — Scope of works

Civil engineering activities shall be undertaken within Aprons 1 and 4 (VIP apron). The scope of works includes interventions on Taxiway Bravo, the southern portion of the Deicing Apron, and the southern section of the VIP Apron. Concurrently, earthworks operations are being conducted in relation to the future development of Parallel Taxiway November. These activities comprise ground preparation, grading, and associated preparatory works necessary for subsequent infrastructure deployment.
Operational Impact
0.1

 — PHASE 2 – Period May 16, 2026 - August 30, 2026

 — Scope of works

Civil engineering works shall be undertaken within the southern airside area, including interventions on Taxiway Alpha and the northern section of the Deicing Apron. In parallel, major civil works will be carried out on the central section of the future Parallel Taxiway November. Temporary connections N3 and N7, linking Taxiway November to Runway 05L-23R, shall be constructed during this phase. Additionally, civil works related to the development of the future Cargo Apron are scheduled to commence. Routine maintenance works on Runway 05R-23L are also planned, consisting of periodic interventions of approximately five (5) hours duration.
Operational Impact
0.1

 — PHASE 3 – Period September 1, 2026 – October 31, 2026

 — Scope of works

Civil engineering works shall be undertaken on Taxilane Kilo 1, including phased rehabilitation interventions. Simultaneously, demolition works shall commence on Runway 05L-23R between Taxiway Delta and Threshold 23R, while maintaining operational continuity via Taxiway Foxtrot and connection N7. Construction activities shall also include the implementation of temporary connections between Taxiway November and Taxiway Lima, as well as November 2 (N2). Works related to the development of the Cargo Apron shall continue during this phase. In addition, routine maintenance works on Runway 05R-23L are scheduled, consisting of interventions of approximately five (5) hours duration.
Operational Impact
0.2

 — PHASE 4 – Period November 1, 2026 – February 28, 2027

 — Scope of works

Civil engineering works shall continue on the development of the Cargo Apron. The scope of demolition works on Runway 05L-23R shall be extended to include the section between Taxiway Charlie and Taxiway Delta, in addition to the segments already under demolition between Taxiway Delta and Taxiway Foxtrot, and between Taxiway Foxtrot and Threshold 23R. Taxiway connections between Runway 05R-23L and Taxiway November shall remain operational throughout this phase. Routine maintenance works on Runway 05R-23L shall no longer be conducted during this phase.
Operational Impact
0.3

 — PHASE 5 – Period March 1, 2027 – May 31, 2027

 — Scope of works

The following construction activities are planned during this phase:
Operational Impact
0.4

 — PHASE 6 – Period June 1, 2027 – August 31, 2027

 — Scope of works

During this phase, civil works are executed on the zones designated as Papa 1 and a segment of Taxiway Lima. Upon completion of works within the Triangle Zone (Phase 5), construction commences on the new Taxiway Papa 1, by establishing connection with Apron 6 and the Triangle Zone. Concurrently, demolition works commence on:
Operational Impact
0.5

 — PHASE 7 – Period September 1, 2027 – November 30, 2027

 — Scope of works

Civil works during this phase concern the permanent connections on N3 and N7. It is important to note that N3 is intervened first, and upon its completion, works on N7 commence. Additionally, civil works are executed on Taxiway Hotel along the segment between Taxiway Bravo and Taxiway Kilo. This effectively restricts the only access to Taxilane K1 to the entry via taxilanes Alpha 2 and Alpha 3. Civil works also commence on the eastern part of the new Cargo Apron.
Operational Impact
0.6

 — PHASE 8 – Period December 1, 2027 – March 31, 2028

 — Scope of works

The only civil works in progress during this phase are on the section of Runway 05L-23R located between Delta and Threshold 05R. The remainder of the aerodrome presents no significant civil works
Operational Impact
0.7
0.8